Builders test whether a system works as designed. User acceptance testing checks whether it works for the people who will use it. The buyer's staff try the system on their real tasks, in conditions close to daily work, and decide whether to accept it. UAT is often the formal gate between the build and go-live, and in many contracts it is tied to the final payment. For buyers, it is the last good chance to find out that the system solves the wrong problem, or solves the right one awkwardly.
How it works
UAT works best when the acceptance criteria are written down before the build starts, ideally in the statement of work. For AI systems, criteria should cover both function and quality:
- Function. The system completes the agreed tasks: it reads the inbox, extracts the fields, updates the CRM, sends the reply.
- Quality. Outputs meet an agreed standard on a defined test set, such as a golden dataset scored by evals.
- Usability. Staff can do their work with it without workarounds.
- Edge cases. Known hard cases are handled, or at least flagged for a person.
Testing usually takes place in a staging environment with realistic data. Testers record issues, the builder fixes them, and the cycle repeats until the buyer signs off. Issues are usually sorted into must-fix before launch and can-fix after.
What it means for cost
UAT costs the buyer staff time, which is easy to forget when budgeting. It also affects the builder's price: vague acceptance criteria make it hard to know when the job is done, so careful builders price in extra rounds of changes. Clear criteria make quotes tighter and disputes rarer.
Under a milestone payment arrangement, UAT sign-off often releases the final payment. Ask a builder:
- What exactly will we test, and what counts as passing?
- How many rounds of fixes are included in the price?
- How will we tell a bug, which you fix, from a new request, which is a change?
- Who will be available during our testing period?
Agreeing the difference between a defect and a change request before UAT starts prevents most arguments at the end.
Common mistakes
Testing with tidy sample data instead of real, messy cases. Leaving UAT to one person who is not a regular user. Signing off under deadline pressure with known problems unrecorded.
Common questions
Who should do user acceptance testing?
The people who will use the system every day, plus someone who can judge whether it meets the business goal. Builders should support testing but not perform it, since the point is an independent check from the user side.
How long should UAT take?
Long enough to run the main tasks several times with realistic data, including the hard cases. For a small automation that can be a few days; for a customer-facing assistant it is usually longer. Plan the time in the project schedule rather than squeezing it in before launch.
What happens if the system fails UAT?
The builder fixes the defects against the agreed criteria and the buyer tests again. If the failure comes from a requirement that was never agreed, it becomes a change request with its own cost and timeline.